Target GP
8059
Target Village
43865
Target Ward
115282
 
 
Total Sanitation Supervisor
6447
Total Route Chart Prepared
46823
Total Swachhata Karmi
111647
User Charges Collection
Total Collected Amount      : Rs. 519540
Total IEC (Wall Painting/Writing)
87572
Total Compost-Pit Constructed
9010
Procurements
IndicatorTargetAchievement
E-Rickshaw Purchased42458039
Padal-Rickshaw Purchased58279108841
Dustbin Purchased 021303932
E-Rickshaw Purchased063300
Liquid Waste Management
IndicatorTargetAchievement
Individual Soakpit Construction067745
Individual Magic-pit Construction02939
Community Soakpit Construction77375153396
Junction Chamber Construction5045483135
Nali Outlet Points Construction2978824688
Total WSP/DuckWeed0743
Total Ward Where Work Started
105775

Download
WPU Reports
Total Land Identified      : 7989
WPU In Progress             : 667
WPU Constructed           : 7152